Jyndabyne Dam




Jindabyne Dam, one of a series of dams that forms part of Australia's famous Snowy Mountains Hydro Electric Scheme had a new 3.6 metre diameter tunnel, training walls, spillway walls and new intake tower added in 2005. The projects is part of a Commonwealth and State initiative to increase the water flow in the Snowy river.

PERI were asked to supply formwork for the new training and spillway walls due to previous expertise shown in doing large single faced forms and single faced climbing systems.

TRIO was the obvious choice for the formwork system, fast efficient with high productivity required due to a short construction program.

For the training wall, TRIO was combined with SB to do the first 7.2m pour, subsequent smaller pours were tied back to the rock or were single sided for the spillway walls. TRIO was combined with SKSF240, this meant no ties through the face and was a faster and more efficient way of constructing the spillway walls.

PERI Systems In Use
  • TRIO
  • SKS Single Sided Climbing System
  • SB Brace Frame
  • Contractor: Bettaform P/L
    Contractor: Kenpass P/L
    Field Service: PERI Australia Pty. Ltd., Australia