Lawrence Hargrave Drive Bridge
Lawrence Hargrave Drive Bridge PERI provided pier formwork and pier head support structures to safely and quickly construct the Lawrence Hargrave Drive Bridge located about a 1 hour drive south of Sydney. The bridge was built up to 45m from the coastal embankments, with the roadway up to 41m above the sea level. PERI SB Brace Frames mounted onto the already poured concrete piers formed a safe working platform, enabling the rapid construction of the pier head structure. VARIO and TRIO wall formwork for the piers mounted on CB240 Climbing Platforms.
|
| PERI Systems In Use |
CB Climbing System
VARIO GT 24 Girder Wall Formwork
PERI UP Rosett
TRIO
SB Brace Frame
|
|
Tony Woods
General Superintendent, LHD Link Alliance
"The PERI Systems used on our project allowed for safe, efficient and cost effective construction solutions to be achieved"
|
|
|
|
|